Skip to content
prop cadence.Your Cadence0/60
← All education

Markets / 6 MIN READ

Micro Futures Tick Value: Work an MES Position

A micro contract is smaller than an E-mini contract. The actual multiplier still determines every price-loss calculation.

PART OF A LEARNING PATHFollow the instrument ↗

Use the specification for the traded contract

CME lists Micro E-mini S&P 500 futures, MES, with a $5 multiplier per index point and a 0.25-point minimum price increment. That makes one outright tick $1.25 per contract. This is an exchange specification, not a universal value for all micro futures.

Record the full contract symbol and expiry, quantity, tick size and tick value from the relevant specification. A prop dashboard’s nominal account size does not change the contract payoff. Do not use an options premium tick or calendar-spread increment as the outright futures increment.

Convert a planned stop in the right order

Assume a hypothetical MES entry and a stop 2.5 index points apart. Divide 2.5 by 0.25 to get ten ticks. Ten ticks × $1.25 = $12.50 per contract. Three contracts create $37.50 gross planned price loss.

If the illustrative round-trip charge is $1.20 per contract, add $3.60 to get $41.10 planned loss. That fee is invented, not CME’s or a prop firm’s price. Actual slippage, taxes or other charges require their own inputs. Keep the arithmetic separate from the account’s permission to hold three contracts.

Original illustrative worksheet
StepCalculationResult
Stop distance2.5 / 0.2510 ticks
One contract10 × $1.25$12.50
Three contracts3 × $12.50$37.50
Assumed costs3 × $1.20$3.60
Planned total$37.50 + $3.60$41.10

Invented values unless a contract specification is explicitly attributed. Only the MES multiplier and outright tick are exchange-attributed; the trade and fee are invented.

Compare the result with every active limit

A calculated dollar deduction is only one part of the account check. A contract cap, scaling band, daily soft stop, hard equity floor or mandatory flatten time can be relevant at the same time. Check the exact evaluation and funded stages separately.

If the nearest supplied boundary leaves $40, a $41.10 planned deduction is already larger than that room under the stated assumptions. The comparison does not become acceptable because the buying-power label says $50,000. Nor does leaving a small arithmetic remainder guarantee a safe fill.

Reconcile the executed trade

Save the instrument month, each fill, total contracts, gross price result, posted charges and the planned stop. Convert the actual price distance through the same multiplier. Check whether the export reports contracts, units or lots before summing quantity.

For micros and minis mixed in one account, obtain the provider’s combined contract-cap conversion rather than inferring it from price exposure alone. Use the futures model in the position tool, then return to the contract guide for instruments with different units or settlement. A correct MES calculation is not a compatibility verdict for every futures programme.

PUT IT INTO PRACTICE

Check your understanding.

MES moves 2.5 index points. At 0.25 points per tick, how many ticks is that?